The Transmission Company of Nigeria (TCN) has announced the successful energisation of two newly installed power transformers at its 330/132/33 kilovolt Birnin Kebbi Transmission Substation in Kebbi State.
This was disclosed in a statement released on Sunday by TCN’s spokesperson, Ndidi Mbah.
According to the statement, the 100 MVA and 150 MVA transformers were energized at 1:18 p.m. and 2:56 p.m., respectively, on Friday, June 27, 2025.
She stated that the installation of the additional transformers has increased the substation’s capacity from 300 MVA to 450 MVA.
As a result, the Kaduna Electricity Distribution Company now has an additional 120 MW of bulk power for distribution to its customers across Kebbi, Sokoto, and surrounding areas. This development also enables TCN to maintain normal bulk power supply to Niamey, Niger Republic.
“We are committed to the continued expansion and maintenance of the nation’s transmission system to ensure a more effective and efficient bulk power transmission nationwide,” the statement reads.