The Lagos State Government has declared the temporary shutdown of the Adekunle Ramp, which connects road users from the Third Mainland Bridge to Ebute Meta in the state.
The closure is due to ongoing construction work on this heavily trafficked route, with the aim of completing it within a five-week timeframe, as stated in an announcement by Mr. Oluwaseun Osiyemi, the Commissioner for Transportation, on Thursday.
The entire traffic entering and exiting the ramp will be restricted from Sunday, November 19, until December 8, marking the designated five-week completion period for the project.
See the full statement below:
LAGOS STATE GOVERNMENTMINISTRY OF TRANSPORTATION
PRESS RELEASE
DIVERSION OF TRAFFIC ON ADEKUNLE RAMP, INWARD AND OUTWARD
Following the level of the construction works ongoing on Adekunle Ramp and to complete it in a record time of Five Weeks, the entire traffic inward and outward of the ramp will close to traffic from Sunday, 19th November till 8th December 2023, (the completion period of 5 weeks earmarked for the project).
Consequently, alternative routes presently in use still subsist as follows;
1. Motorists from Lagos Island heading to Ebute Meta will make use of Ilubirin to connect Carter Bridge (Idumota Bridge) to link Iddo inwards Otto/Oyingbo axis and access Herbert Macaulay Way to link their desired destinations.
2. Motorists from Victoria Island are to go through Bonny Camp to Onikan Marina Bridge, Apongbon to link Eko Bridge, Costain via Apapa Road, Railway Compound to link Alagomeji, Glover Road to access Apena Junction, Herbert Macaulay Way to connect their desired destinations.
3. In the same vein, Motorists wishing to travel through Adekunle to Ebute- Meta from Lagos- Ibadan are advised to make use of Ikorodu Road (Ojota, Anthony, Onipanu, Fadeyi) and Jibowu to access Herbert Macaulay Way to continue their journeys.
4. Motorists from Gbagada can go through Anthony Interchange to link Ikorodu Road inwards to Jibowu to access Herbert Macaulay Way and link their desired destinations.
5. Motorists from Apapa-Oshodi Expressway wishing to link Ebute-Meta are advised to link Oshodi Bridge to Town Planning Way to Ikorodu Road to access their various destinations
Adequate traffic and security personnel are still on the ground at the construction zones and the various alternative routes/critical points, Motorists are encouraged to cooperate with them, exercise patience, and observe safety measures during the palliative works.
It should be noted that the entire stretch of the 3rd Mainland Bridge inward and outward is still open to Motorists during this period as only the Adekunle ramp is affected.
E-signed;Mr. Oluwaseun Osiyemi,Lagos State Commissioner for Transportation.16th November, 2023.